Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
August 2013 – End of Construction

Friday, November 22, 2013

Asphalt Paving Completed. Remaining Driveway Restorations to be completed by Thanksgiving


This past week, Arrow Road, the paving contractor completed paving the asphalt surface along Longmeadow Drive from East Lake Avenue to Bellwood Lane, Bellwood Lane, and Ralmark Lane.

The paving contractor also completed the asphalt driveway restorations on the north side of East Lake Avenue along Longmeadow Drive, Bellwood Lane, and Ralmark Lane. The asphalt driveways restorations along Longmeadow Drive south of East Lake Avenue have started and are scheduled to be completed before the Thanksgiving Holiday.

Landscape sub-contractor was also on-site continuing to grade and install topsoil along Longmeadow Drive and Ralmark Drive. The landscaper is anticipating to have all landscape grading and topsoil installation completed by the Thanksgiving Holiday also.

Due to the current weather conditions and work going late into the construction season, the installation of sod north of East Lake Avenue will not occur this year. We believe the growing conditions will be more favorable and the final product will be much better if we wait until next spring to install the sod. We apologize for the inconvenience this may cause, but feel it is the best decision.

We continue to appreciate your patience and understanding throughout this extended construction season for all of you.

Have a safe and happy Thanksgiving.

This will be the last Blog Update for this year. We would like to thank all of you who took the time to read the posts. We hope that you have found this information provided useful and informative.

If you have any additional questions or concerns, please contact Robert Steele, Project Manager, at 847-904-4423.

Friday, November 15, 2013

Asphalt Surface South of East Lake Avenue Completed

This past week, Arrow Road, the paving contractor completed paving the asphalt surface along Longmeadow Drive, between Glenview Road and East Lake Avenue.

North of East Lake Avenue along Bellwood Lane, Ralmark Lane, and Longmeadow Drive, the landscaping contractor graded and installed topsoil behind the concrete curb & gutter. Arrow Road performed some asphalt base patching along Bellwood Lane and Greenwood Road. Arrow Road also began driveway restorations along Bellwood Lane including removing the existing pavement and installing the lower layer of asphalt.

The underground sub-contractor was also on-site adjusting manhole frames and lids in preparation of asphalt surface paving.

Next week, Arrow Road is scheduled to pave the asphalt surface along Bellwood Lane, Ralmark Lane, and Longmeadow Drive north of East Lake Avenue. Depending on weather, this work will either begin on Monday or Tuesday and be completed by Tuesday. The contractor will then complete the asphalt driveway restorations along the entire project site on both sides of East Lake Avenue. We anticipate all asphalt driveways will be restored by the end of the week.

Due to the current weather conditions, we are evaluating the options to determine whether or not the sod north of East Lake Avenue will be installed this fall or if it will be better to wait until early next spring.

We continue to appreciate your patience and understanding as we are working diligently to ensure as much work as possible is completed this year. We have been in constant contact with the contractors to determine their schedules and to ensure this project continues to be a priority.

Monday, November 4, 2013

Pavement Milling / Removal Completed

Last week the concrete sub-contractor, D’Land Construction, completed the concrete work on the north side of East Lake Avenue including opening of driveways. Arrow Road Construction completed the removal / milling of the existing asphalt pavement on both sides of East Lake Avenue. On the south side of East Lake Avenue, the contractor performed a 2-inch surface mill. On the north side of East Lake Avenue, the contractor performed a full-depth, 4-inch, pavement removal.

The contractor was on-site performing some rough grading along the north side of East Lake Avenue to make the transitions between the existing pavement and aggregate base course smoother and also remove some of the bumps creating during the full depth pavement removal process. On the south side of East Lake Avenue, residents will continue to drive on the rough “grooved” surface until the asphalt paving is completed.

This week, the remaining concrete work along the project site will be completed along with a few additional repairs that need to be completed prior to asphalt paving. The roadways will also be evaluated to determine if any repairs need to be made to the remaining asphalt pavement or aggregate base course prior to paving.

 Arrow Road will fine grade the existing base course on the north side of East Lake Avenue. Arrow Road is anticipating to perform asphalt binder and surface paving on both the north and south sides of East Lake Avenue.

We ask that all vehicles be removed from the roadway during work hours, 7:00 AM to 5:00 PM.

The landscape restoration along the north half of the project will be completed following the asphalt paving process.

We continue to expression our gratitude for your patience during the construction operations. We continue to request your cooperation during the roadway grading and asphalt paving process.

Friday, October 25, 2013

Pavement Milling to Begin

This past week the concrete sub-contractor, D’Land Construction, completed the concrete curb & gutter, sidewalk, and driveway installation along the south side of Bellwood Lane, east side of Longmeadow Drive, and north and west sides of Ralmark Lane. The contractor has not yet back-filled in front of the curb & gutter to allow sufficient time for the concrete to cure. Please do not drive on the new curb& gutter or concrete driveways until the barricades are removed and the area in front of the curb & gutter is filled with aggregate. Asphalt driveways will be temporarily ramped with aggregate until they are fully restored after the asphalt roadway surface is installed.

Last week, Glenbrook Excavating was also on-site performing repairs associated with the underground utility work that were indicated on their punch list.

Next week, Arrow Road will be on-site to begin the pavement removal and milling process on the north and south side of East Lake Avenue. The contractor will remove 2-inches from the existing asphalt pavement along Longmeadow Drive and adjoining streets south of East Lake Avenue. It is anticipated a layer of asphalt pavement will remain on these sections of the roadway. Residents will be driving on asphalt, but it will be “grooved” and rough. Once the asphalt milling process is completed and all required base repairs are completed, the contractor will begin paving the new asphalt surface.

The contractor will remove 4-inches of the existing asphalt surface along Longmeadow Drive, Ralmark Lane, and Bellwood Lane north of East Lake Avenue. It is anticipated this will remove the entire existing asphalt pavement to the existing aggregate base course. Residents will be driving on a gravel roadway until the roadway can be graded and the asphalt binder is installed. Following the pavement milling, the existing aggregate base will be graded and compacted. Once the aggregate base work is completed, the asphalt binder and surface layers will be installed.

We ask that all vehicles be removed from the roadway on the days scheduled for work within the roadway. Additional information will be provided to residents regarding anticipated work schedule, parking restrictions, and access to driveways.

The landscape restoration along the north half of the project will be completed following the asphalt paving process.

We continue to expression our gratitude for your patience during the construction operations. Your cooperation with the inconvenience associated with the concrete curb & gutter construction was greatly appreciated. We continue to request your cooperation during the asphalt removal and paving process.

Friday, October 18, 2013

Concrete Curb & Gutter Replacements Continue on Bellwood Lane, Longmeadow Drive, and Ralmark Lane

The project has been transitioned from Glenbrook Excavating, the underground contractor who performed the water main and storm sewer improvements, to Arrow Road. Arrow Road is the general contractor for the Village’s 2013 Road Resurfacing Project (also called MFT). D’Land Construction is a sub-contractor for Arrow Road that will be performing the concrete work.

This past week the concrete sub-contractor, D’Land Construction, completed the concrete curb & gutter and driveway installation along the north side of Bellwood Lane, west side of Longmeadow Drive, and south and east sides of Ralmark Lane. The contractor also installed temporary aggregate base course in front of the previously installed concrete curb & gutter and asphalt driveways to allow access to homes and allow for parking.

The contractor had initially planned to begin concrete curb & gutter replacement on the remaining portions of Bellwood Lane, Longmeadow Drive, Ralmark Lane this week. Unfortunately, due to the rainy weather conditions the process has been delayed. It has been decided to wait to remove the concrete curb & gutter beginning Monday, October 21st to minimize the amount of time residents are not allowed to access their driveways.

Information has been provided to residents north of East Lake Avenue regarding parking restrictions and driveway access during the concrete curb & gutter replacement process. If the curb & gutter in front of your home is scheduled to be removed, please have all cars removed from the driveways prior to 7:00 AM on Monday, October 21st.

Concrete driveways will be restored following the concrete curb & gutter installation. Asphalt driveways will be restored during the asphalt paving stage of the project. Temporary aggregate will be installed in front of all driveways to allow for access following concrete cure time.

We understand the residents south of East Lake Avenue have not seen any construction activity for an extended period of time. We have been in contact with the paving contractor regarding timing and construction of the asphalt surface along Longmeadow Drive from Glenview Road to East Lake Avenue. At this time, the best option is to wait until the concrete replacements north of East Lake Avenue are completed prior to milling the existing surface and asphalt paving for the entire project limits. We apologize for the inconvenience this has caused. We are still committed to and expect to complete all the asphalt paving this construction season.

We continue to expression our gratitude for your patience during the construction operations. Your cooperation with the inconvenience associated with the concrete curb & gutter construction is greatly appreciated.

Friday, October 11, 2013

Concrete Curb & Gutter Replacements On-Going north of East Lake Avenue

The project has been transitioned from Glenbrook Excavating, the underground contractor who performed the water main and storm sewer improvements, to Arrow Road. Arrow Road is the general contractor for the Village’s 2013 Road Resurfacing Project (also called MFT). D’Land Construction is a sub-contractor for Arrow Road that will be performing the concrete work.

This past week D’Land construction removed the existing concrete curb & gutter on the north side of Bellwood Lane, west side of Longmeadow Drive, and south and east sides of Ralmark Lane. D’Land also begin installing the concrete curb & gutter in these areas.  The concrete work in these areas of the roadway will continue early next week with the completion of the concrete curb & gutter and concrete driveway installation.

Next week, the contractor will allow the newly installed concrete to cure. The contractor will then move to the opposite sides of the street to begin concrete curb & gutter removal and replacement. Additional notification and parking restrictions will be provided when a firm schedule is determined.

All the roadways within the project limits, including Longmeadow Drive from Glenview Road to East Lake Avenue (area south of East Lake Avenue), Longmeadow Drive from East Lake Avenue to Bellwood Lane (area north of East Lake Avenue), Bellwood Lane from Executive Court to Greenwood Road, and Ralmark Lane from Bellwood Lane to Longmeadow Drive will have the existing asphalt surface milled and repaved as part of this project. This work will not take place until after the concrete curb & gutter replacement north of East Lake Avenue are completed. We are currently working with the contractors to determine the exact start date for the roadway resurfacing, but we are anticipating the work will begin 2 to 3 weeks.

The sod north of East Lake Avenue will not be installed until the concrete curb & gutter and roadway work is completed.

We continue to expression our gratitude for your patience during the construction operations. Your cooperation with the inconvenience associated with the concrete curb & gutter construction is greatly appreciated.

Monday, October 7, 2013

Concrete Curb & Gutter to Begin This Week

This past week the contractor completed installing and grading topsoil in the disturbed areas north of East Lake Avenue. Construction staking in preparation for concrete  curb & gutter was also performed. Village staff started performing the final walk-through to identify any repairs required associated with the underground utility improvements. The final walk-through will hopefully be completed within the next week or so, depending on weather.

The sod north of East Lake Avenue will not be installed until the concrete curb & gutter and roadway work is completed.

Concrete curb & gutter removal along the north side of Bellwood Lane, west side of Longmeadow Drive, and south and east sides of Ralmark Lane is anticipated to begin mid next week, depending on weather conditions.  More information will be provided regarding driveway access and parking while the concrete curb & gutter work is on-going.

We continue to expression our gratitude for your patience and understanding during this long construction season.

Monday, September 30, 2013

Concrete work North of East Lake Avenue to Begin week of October 7th

This past week the contractor completed miscellaneous tasks and clean-up along the entire project site.

The contractor also continued grading and installing topsoil north of East Lake Avenue.

Next week, the landscape sub-contractor will complete the installation and grading of topsoil north of East Lake Avenue. The sod in this area will not be installed until the concrete curb & gutter and roadway work is completed.

The landscape sub-contractor has continued to water the previously installed sod south of East Lake Avenue. The contractor will continue to water until the sod is established and healthy.

We have spoken with the contractor who will be performing the roadway improvements portion of the project. The concrete sub-contractor is expected to begin full concrete curb & gutter removal and replacement north of East Lake the week of October 7th. More information will be provided regarding access to driveways and parking restrictions during concrete curb & gutter work later this week.

We continue to expression our gratitude for your patience and understanding during this long construction season. As stated previously, the underground utility improvements portion of the project is completed, we are now transitioning to the roadway improvements portion.

Friday, September 20, 2013

Underground Utility Construction Completed.

North of East Lake Avenue: The contractor completed the storm sewer improvements along Ralmark Lane, Bellwood Lane, and Longmeadow Drive. The contractor also performed general site clean-up, removal of construction equipment, and rough grading of the landscape areas.

Last week, south of East Lake Avenue, the landscaping sub-contractor completed the sod installation. The contractor also completed some minor work to adjust fire hydrants and valve boxes. 
 
All underground utility work has now been completed for the project. The remaining items associated with this contract to be completed include grading and installing topsoil, site clean-up, adjustments of structures and fire hydrants, remaining water main testing, and other miscellaneous tasks. The contractor is currently scheduled to be on-site through the middle of next week performing most of this remaining work and complete this portion of the construction.

The landscape sub-contractor is currently scheduled to install and grade topsoil north of East Lake Avenue next week. The contractor will install the topsoil within 2 feet of the existing curb & gutter. Sod will not be installed until after the roadway work has been completed.

All roadways within the project limits will be rehabilitated with the 2013 Road Improvement Program. We are currently working with the contractor to get this work scheduled.

We understand this has been a long summer of construction for all the residents. We appreciate all of your patience and understanding as the underground utility work is complete and we transition to the roadway rehabilitation phase of the project.

Monday, September 16, 2013

Water Main Improvements Completed

North of East Lake Avenue: The contractor completed the remaining water main work including installing water services along Bellwood Drive and Longmeadow Drive and making the final connections between the new and existing water main systems. The contractor also installed the new storm sewer along Longmeadow Drive from Bellwood Lane to Ralmark Lane.

Last week, south of East Lake Avenue, the contractor completed the asphalt trench patching within the roadway. The landscaping contractor also completed the grading and installation of topsoil. The contractor also completed some miscellaneous repairs and site clean-up.

South of East Lake Avenue: The landscape sub-contractor is anticipated to begin installing sod on Monday, September 16th. We appreciate your patience with the sod installation and waiting for more favorable growing conditions.

North of East Lake Avenue: Next week, the contractor will continue to complete storm sewer installations along Bellwood and Ralmark Lane. The landscaping sub-contractor will also begin grading and installing topsoil in preparation for sod restoration.

All of the water main installation, including water services and connections to the existing system are completed for the entire project.

The remaining underground utility work remaining includes storm sewer installations and repairs on the north side of East Lake Avenue.

The contractor is currently scheduled to be completed with all underground utility improvements by September 20th.

Once the underground utility improvements are completed, the roadway will be rehabilitated with the 2013 Road Improvement Program.

Thank you for your patience during the construction operations and numerous interruptions to your water service throughout the project. We are nearing the end of the underground utility improvements of the project and will soon be concentrating on the landscape restoration and roadway rehabilitation.

Friday, September 6, 2013

Trench Paving on South Side, Water Services on North Side

North of East Lake Avenue: This past week the contractor received test results and required approvals prior to installing water services. Water services were installed to individual homes along Bellwood Lane from Ralmark Lane to Greenwood Road and Longmeadow Drive from Ralmark Lane to East Lake Avenue.

Last week, south of East Lake Avenue, the contractor performed some miscellaneous storm sewer repairs. The contractor also continued to grade, cut, and install topsoil in preparation of sod installation. Asphalt trench patching also began along Longmeadow Drive.

South of East Lake Avenue: Next week, the landscape sub-contractor is anticipated to complete grading and installing topsoil in preparation for sod installation. Depending on the weather conditions, the contractor may begin installing sod. Otherwise, the contractor will wait until the weather is cooler for more favorable growing conditions. The contractor is also anticipated to complete the asphalt pavement trench patching along the roadway.  The contractor will also begin performing continuity and leakage testing on the new water main.

North of East Lake Avenue: Next week, the contractor will complete the water service installations along Longmeadow Drive. The contractor will also begin making connections and disconnections to the existing water system at various locations. The connections between the existing water main and new water main will require sections of the water main to be shut-off. The contractor will also begin the storm sewer improvements within the area.

Residents will be notified at least 24-hours in advance of any scheduled water main shut-down. 

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off. The contractor will attempt to give each resident approximately 1 hour notice prior to turning off the water to install the water service.

The contractor is currently scheduled to be completed with all underground utility improvements by September 20th. Once the underground utility improvements are completed, the roadway will be rehabilitated with the 2013 Road Improvement Program.

Thank you for your patience during the construction operations.

Friday, August 30, 2013

Concrete Curb & Gutter Completed on South Side

North of East Lake Avenue: This past week the contractor installed water services to individual homes along Ralmark Lane, Bellwood Lane from Ralmark to Executive Drive, and Longmeadow from Ralmark to Bellwood. The contractor also completed the required testing of the new water system. Once the results of those tests are returned and proper approvals are acquired, the remaining water services along Bellwood Lane and Longmeadow Drive will be completed. The contractor also completed some general clean-up along the site.

Last week, south of East Lake Avenue, the contractor completed the concrete curb & gutter repairs. The contractor also graded, cut, and installed topsoil in preparation of sod installation. The contractor also completed general clean-up along the project site.

South of East Lake Avenue: Next week, the landscape sub-contractor will continue to grade and install topsoil in preparation for sod installation. Depending on the weather conditions, the contractor may begin installing sod. Otherwise, the contractor will wait until the weather is cooler for more favorable growing conditions. The contractor will also begin performing asphalt trench patching and a few other miscellaneous repairs.

North of East Lake Avenue: Next week, the contractor will complete the water service installations once all of the test results and required approvals are received. The contractor will also begin making connections and disconnections to the existing water system at various locations. The connections between the existing water main and new water main will require sections of the water main to be shut-off. The storm sewer improvements are also anticipated to begin.

Residents will be notified at least 24-hours in advance of any scheduled water main shut-down. 

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off. The contractor will attempt to give each resident approximately 1 hour notice prior to turning off the water to install the water service.

Thank you for your patience during the construction operations.

Monday, August 26, 2013

Concrete Curb & Gutter South of East Lake Ave On-Going

This past week the contractor installed water services to individual homes along Ralmark Lane from Longmeadow Drive towards Bellwood Lane and along Bellwood Drive.

Last week, south of East Lake Avenue, the contractor graded the existing landscape, removed the existing concrete curb & gutter, excavated for curb & gutter, and installed concrete curb & gutter in areas marked to be replaced.

South of East Lake Avenue: Next week, the contractor will complete the concrete curb & gutter replacements on both sides of the roadway, continue with landscape grading, installation of topsoil, and complete the miscellaneous underground utility improvements.

North of East Lake Avenue: The contractor will continue to perform the required testing on the remaining sections of water main not previously tested. The contractor will continue to install water services along Bellwood Lane, Ralmark Lane, and Longmeadow Drive in areas that have been previously tested and approved.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off. The contractor will attempt to give each resident approximately 1 hour notice prior to turning off the water to install the water service.

Thank you for your patience during the construction operations.

Monday, August 19, 2013

Curb & Gutter to Begin South of East Lake Avenue

This past week the contractor installed water main along Bellwood Lane at the Greenwood Road intersection, near Longmeadow Drive and East Lake Avenue, and within the East Lake Avenue easement near the pedestrian bridge. The contractor also began installing new water services to homes north of East Lake Avenue where the existing water main has been tested.

Last week, south of East Lake Avenue, no work was performed on-site.

South of East Lake Avenue: Next week, the contractor is anticipating to complete the storm sewer improvements. The contractor will also complete the abandonment of the fire hydrants and water valves on the old water main system.

The contractor will begin spot concrete curb & gutter removal and replacements on Longmeadow Drive south of East Lake Avenue next week. Additional information will be passed along to residents regarding the procedures during this process, including parking restrictions and access to driveways.  

North of East Lake Avenue: The contractor will begin performing the required testing on the remaining sections of water main not previously tested. The contractor will continue to install water services along Bellwood Lane, Ralmark Lane, and Longmeadow Drive in areas that have been previously tested and approved.

The contractor has scheduled to bring a second crew to help with water services on the north side of East Lake Avenue starting on Friday, August 16th. Starting on Monday, August 19th, a third crew is scheduled to be on-site working on the south side of East Lake Avenue performing the remaining underground utility work and begin removing the concrete curb & gutter marked to be replaced. Immediately following the concrete curb & gutter removal, the concrete sub-contractor will be on-site to begin forming and pouring the new concrete curb & gutter.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off. The contractor will attempt to give each resident approximately 1 hour notice prior to turning of the water to install the water service.

Thank you for your patience during the construction operations.

Monday, August 12, 2013

Directional Drilling Complete

This past week the contractor installed water main along Bellwood Lane between Ralmark Lane and Greenwood Road, made the connection to the existing system along Longmeadow Drive (North) and Bellwood Lane that leads to St. Catherine’s Church and School, and performed directional drilling of the 12-inch water main along the East Lake Avenue Easement. All of the water main scheduled to be installed via directional drilling has been completed. The remaining water main installation will be installed via open cut methods.

Last week, south of East Lake Avenue, no work was performed on-site.

South of East Lake Avenue: Next week, the contractor is anticipating to complete the storm sewer improvements. The contractor will also complete the abandonment of the fire hydrants and water valves on the old water main system.

The contractor will begin spot concrete curb & gutter removal and replacements on Longmeadow Drive south of East Lake Avenue in the near future. Additional information will be passed along to residents regarding the procedures during this process, including parking restrictions and access to driveways.  

North of East Lake Avenue: Next week, the contractor will complete the water main installation at the Bellwood and Greenwood Road intersection and installation of water main along Longmeadow Drive near East Lake Avenue. The contractor will also begin performing the required testing on the remaining sections of water main not previously tested. The contractor will likely begin installing water services later in the week within the areas of water main previously tested and ready for water service installation.  

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off. The contractor will attempt to give each resident approximately 1 hour notice prior to turning of the water to install the water service.

Thank you for your added patience and cooperation on Wednesday during an unanticipated water main shut down that effected most of the project site north of East Lake Avenue due to complications encountered while making the connection to the St. Catherine’s Church & School.

Thank you for your patience during the construction operations.

Friday, August 2, 2013

Water Main Along Greenwood Road On-Going

This past week the contractor performed water main testing along Bellwood, Ralmark, and Longmeadow Drive north of East Lake Avenue. The contractor also installed water main along Longmeadow Drive south of Ralmark Drive and along Greenwood Road from Bellwood to the south, including directional drilling under Greenwood Road.

Last week, south of East Lake Avenue, no work was performed on-site.

South of East Lake Avenue: Next week, the contractor is anticipating to complete the storm sewer improvements. The contractor will also complete the abandonment of the fire hydrants and water valves on the old water main system.

The contractor will begin spot concrete curb & gutter removal and replacements on Longmeadow Drive south of East Lake Avenue in the near future. Additional information will be passed along to residents regarding the procedures during this process, including parking restrictions and access to driveways.  

North of East Lake Avenue: Next week, the contractor will continue to install the water main along Greenwood Road and Bellwood Road. The contractor is also anticipating to directionally drill the water main in the East Lake Avenue Easement west of Longmeadow Drive. The contractor will also likely begin water service installations along Bellwood Lane.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

Thank you for your patience during the construction operations.

Friday, July 26, 2013

Water Main Installation along Greenwood Road to Begin

This past week the contractor installed water valves and vaults, fire hydrants, and made connections between with previously directionally drilled water mains along Ralmark Lane and Bellwood Drive north of East Lake Avenue. Testing of the new water main system also began last week.  

The contractor also completed directional drilling a new 12-inch water main along Bellwood Lane from Ralmark Lane to Greenwood Road.

Last week, south of East Lake Avenue, the contractor performed various spot repairs to the existing storm sewer and began removing or abandoning fire hydrants and water valves on the old water main system.

South of East Lake Avenue: Next week, the contractor is anticipating to complete the storm sewer improvements. The contractor will also complete the abandonment of the fire hydrants and water valves on the old water main system.

The contractor will begin spot concrete curb & gutter removal and replacements on Longmeadow Drive south of East Lake Avenue the week of August 5th. Additional information will be passed along to residents regarding the procedures during this process, including parking restrictions and access to driveways.  

North of East Lake Avenue: Next week, the contractor will continue the water main testing on the previously installed water main along Bellwood Lane, Ralmark Lane, and Longmeadow Drive. The contractor may begin water services along these roadways should all of the required tests pass.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

The contractor will also directionally drill a new 16-inch water main across Greenwood Road and begin installing a new 16-inch water main approximately 250 south of Bellwood Lane on the east side of Greenwood Road.

Thank you for your patience during the construction operations.

Friday, July 19, 2013

Water Main Installation On-Going North of East Lake Avenue

This past week the contractor installed water valves and vaults, fire hydrants, and made connections between with previously directionally drilled water mains along Bellwood Lane, Ralmark Lane, and Longmeadow Drive north of East Lake Avenue.   

The contractor also completed the directional drilling of the new water main along Ralmark Lane from the cul-de-sac to Bellwood Lane.

No work was completed last week south of East Lake Avenue.

South of East Lake Avenue: Next week, the contractor is anticipating to complete the storm sewer improvements. The contractor will then begin and concrete curb & gutter replacements and paving of the stone trenches. Residents will be notified if any work will affect the access to their driveways.

North of East Lake Avenue: Next week, the contractor will perform water main testing on the previously installed water main along Bellwood Lane and Longmeadow Drive. The contractor will also continue to install fire hydrants, water valve and vaults, and make connections between the previously directional drilled water main along Ralmark Lane. The contractor will also begin directional drilling along Bellwood Lane from Ralmark Lane to Greenwood Road.

Due to the extreme heat conditions, the contractor did work reduced hours throughout the week and did not work on Friday, July 19th.

Thank you for your patience during the construction operations.

Saturday, July 13, 2013

Water Main South of East Lake Avenue Complete

This past week the contractor completed the transferring of water services to the new water main along Longmeadow Drive south of East Lake Avenue. The contractor also completed the connections to the existing water main at Knollwood Lane and Crestwood Lane. The new water main has been completely installed and is 100% operational along Longmeadow Drive from East Lake Avenue to Glenview Road.  

This past week, the contractor also installed water valve vaults, fire hydrants, connections between the previously directionally drilled water main, and connected to the existing water main at Bellwood Lane and Executive Court. The contractor also began directional drilling the new water main along Ralmark Lane on the easterly side from the cul-de-sac to Bellwood Lane.

South of East Lake Avenue: Next week, the contractor is anticipating to complete the storm sewer repairs. The contractor will then begin and concrete curb & gutter replacements and paving of the stone trenches.

North of East Lake Avenue: Next week, the contractor will complete the directional drilling of the water main along Ralmark from the cul-de-sac to Bellwood Lane. The contractor will also begin directional drilling along Bellwood Lane from Ralmark Lane to Greenwood Road. Work will continue along Longmeadow and Bellwood installing the water valve vaults, fire hydrants, and making connections to the previously directionally drilled sections of pipe. Testing of the new water main will likely begin next week prior to starting to install new water services.  

Thank you for your patience during the construction operations.

Monday, July 8, 2013

Water Main Nearly Complete South of East Lake Avenue

This past week the contractor continued to install new water services to individual homes along Longmeadow Drive between Crestwood Lane and East Lake Avenue. The contractor also directionally drilled the new water main along Ralmark Lane from the cul-de-sac to Longmeadow Drive. 

South of East Lake Avenue: The contractor will complete installing the new water services along Longmeadow Drive. The contractor is also anticipating making the connection between the new and existing water mains at the intersections of Knollwood Lane and Crestwood Lane. A water shut down will be required for this work. Residents will be notified 24-hours in advance of any scheduled water main shut down.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

North of East Lake Avenue: The contractor will directionally drill the new water main along Ralmark Lane from the cul-de-sac to Bellwood Drive. The contractor may also begin directional drilling along Bellwood Drive from Ralmark Lane across Greenwood Road.  The contractor will begin installing water valves and fire hydrants along the new water main previously directionally drilled in this area.

Thank you for your patience during the construction operations.

Friday, June 28, 2013

Water Services South of East Lake Avenue Continue

This past week the contractor performed testing on the newly installed water main along Longmeadow Drive between Crestwood Lane and East Lake Avenue. The contractor also continued to install new water services to individual homes along Longmeadow Drive between Knollwood Lane and Crestwood Lane and performed various storm sewer work along Longmeadow Drive between Knollwood Lane and East Lake Avenue. All water services along Longmeadow Drive from Glenview Road to Crestwood Lane have been transferred to the new water main. The contractor did not perform any directional drilling this week in an effort to get caught up with some of the other work associated with the project. 

Next week the contractor will directional drill new water main along Ralmark Lane from Longmeadow Drive to the cul-de-sac.  Water services along Longmeadow Drive from Crestwood Lane to East Lake Avenue will also begin. The contractor is also anticipating making the connection between the new and existing water mains at the intersection of Knollwood Lane and Longmeadow Drive, a water shut down will be required for this work. Residents will be notified 24-hours in advance of any water main shut down.

The contractor will not be working on Thursday, July 4th and is not anticipating performing any work on-site on Friday July 5th.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

Thank you for your patience during the construction operations.

Friday, June 21, 2013

Water Services and Water Main Work Continues

This past week the contractor completed directional drilling the new water main along Bellwood Drive from Executive Lane to Ralmark Lane. The contractor continued to install new water services to individual homes along Longmeadow Drive between Glenview Road and Crestwood Lane.

Next week the contractor will complete testing on the newly installed water main along Longmeadow Drive from Crestwood Lane to East Lake Avenue. Water services will continue to be installed along Longmeadow Drive between Knollwood Lane and Crestwood Lane. Water main will be directionally drilled along Ralmark Lane from Longmeadow Drive to Bellwood Lane. The contractor may also begin installing fire hydrants and water valves on the previously installed water main north of East Lake Avenue.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

Thank you for your patience during the construction operations.

Friday, June 14, 2013

Water Services Continue

This past week the contractor completed directional drilling the new water main along Longmeadow Drive north of East Lake Avenue and began directional drilling along Bellwood Lane from Longmeadow Drive to Ralmark Lane. The contractor also performed the required water main testing for the newly installed water main along Longmeadow Drive between Glenview Road and Crestwood Lane. The contractor began installing new water services to individual homes along Longmeadow Drive between Glenview Road and Knollwood Lane. The contractor did make the connection to the existing water main along the south side of East Lake Avenue at Longmeadow Drive.

Next week the contractor will complete testing on the newly installed water main along Longmeadow Drive from Crestwood Lane to East Lake Avenue. Water services will continue to be installed along Longmeadow Drive between Glenview Road and Crestwood Lane. Water main will continue to be directionally drilled along Bellwood Lane from Executive Court to Longmeadow Drive and along the southerly section of Ralmark Lane from Longmeadow Drive.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

Thank you for your patience during the construction operations.

Friday, June 7, 2013

Water Services South of East Lake Avenue to Begin

This past week the contractor completed directional drilling the new water main along Longmeadow Drive south of East Lake Avenue and began directional drilling along Longmeadow Drive north of East Lake Avenue. The contractor also installed water valve vaults and fire hydrants along the newly installed main.  The contractor installed storm sewer at the intersection of Longmeadow Drive and Crestwood Lane.

Next week the contractor will complete testing on the newly installed water main along Longmeadow Drive from Crestwood Lane to Glenview Road and continue to directionally drill water main along Longmeadow Drive and Bellwood Lane north of East Lake Avenue.

The contractor will also connect the new water main to the existing water main on the north end of Longmeadow Drive, just south of East Lake Avenue. A water main shut down will be required for this work. Residents effected by the shut-down will be notified.

Next week the contractor will begin installing new water services to individual homes along Longmeadow Drive south of East Lake Avenue from Glenview Road to the north.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

Thank you for your patience during the construction operations.

Friday, May 31, 2013

Water Main Installation Continues

This past week the contractor continued to directional drill new water main along Longmeadow Drive south of East Lake Avenue. The water main is installed from Glenview Road to Crestwood Lane. The contractor also installed water valve vaults and fire hydrants along the newly installed main.  The contractor installed storm sewer at the intersection of Longmeadow Drive and Knollwood Lane.

Next week the contractor will perform testing on the newly installed water main along Longmeadow Drive from Crestwood Lane to Glenview Road.  The contractor will also continue to directionally drill water main along Longmeadow Drive from Crestwood Lane to East Lake Avenue and install water valve vaults and fire hydrants after the main is installed.  The contractor also anticipates installing the storm sewer at the intersection of Crestwood Lane and Longmeadow Drive.

Mid next week, the contractor is anticipating to move to the north side of East Lake Avenue to begin directionally drilling the water main along Longmeadow Drive, Ralmark Lane, and Bellwood Lane. The exact location for starting to directional drilling the water main is unknown at this time.  

Once the water main tests have passed, the contractor will begin installing new water services to each residence along Longmeadow Drive from Glenview Road to Crestwood Lane. This process may begin late next week, but more likely the beginning of the week of June 10th.

Thank you for your patience during the construction operations.

Friday, May 24, 2013

Water Main Directional Drilling On-Going

This past week the contractor continued to directional drill new water main along Longmeadow Drive south of East Lake Avenue. The contractor also made the connection to the existing water main at Glenview Road along with installing valve vaults and fire hydrants in the areas the water main was previously installed.

Next week the contractor will continue to directional drill new water main along Longmeadow Drive south of East Lake Avenue.  The contractor will continue installing water valve vaults and fire hydrants on the newly installed water main.

As you are likely aware, during construction operations sometimes unexpected events occur, specifically hitting or breaking an existing water main. If this should occur, the existing water main needs to be shut down immediately and repaired. We will do our best to notify each resident prior to completing turning off the water, but we ask for your understanding and patience during these times.

Residents will be given a 24-hour notice for any scheduled water main shut-downs.

Thank you for your patience during the construction operations.

Friday, May 17, 2013

Directional Drilling Water Main on Longmeadow Drive

This past week the contractor excavated for existing gas, water, and sanitary services in preparation for directional drilling the new water main along Longmeadow, Bellwood, and Ralmark north of East Lake Avenue. The contractor also directional drilled the new water main along Longmeadow Drive from Glenview Road to Knollwod Lane.

Next week the contractor will continue to directional drill new water main along Longmeadow Drive between Crestwood Lane and Knollwood Lane.  The contractor will also begin installing water valve vaults and fire hydrants on the newly installed water main. There is a possibility the existing water main will need to be shut down next week to perform some of the construction operations.  Should this occur, residents will be notified 24 hours in advance.

Thank you for your patience during the construction operations.

Friday, May 10, 2013

Water Main Directional Drilling to Start Next Week

This past week the contractor excavated for existing gas, water, and sanitary services in preparation for directional drilling the new water main.  The contractor also performed televising of the storm and sanitary sewers.

Next week the contractor is anticipating beginning directional drilling the new water main along Longmeadow Drive starting at Glenview Road and going north.


Thank you for your patience during the construction operations.

Monday, May 6, 2013

The contractor, Glenbrook Excavating, is anticipating to perform work in preparation of installing water main along Longmeadow Drive from Glenview Road to East Lake Avenue. Work includes televising the storm and sanitary sewer, project layout, mobilization of equipment, and excavation for existing utilities.

Tuesday, April 16, 2013

Construction is almost upon us.

Residents are invited to attend a preconstruction meeting at the Village of Glenview Police Department Community Room on Tuesday, April 23, 2013 from 7:30 pm to 8:30 pm.