Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
August 2013 – End of Construction

Friday, July 26, 2013

Water Main Installation along Greenwood Road to Begin

This past week the contractor installed water valves and vaults, fire hydrants, and made connections between with previously directionally drilled water mains along Ralmark Lane and Bellwood Drive north of East Lake Avenue. Testing of the new water main system also began last week.  

The contractor also completed directional drilling a new 12-inch water main along Bellwood Lane from Ralmark Lane to Greenwood Road.

Last week, south of East Lake Avenue, the contractor performed various spot repairs to the existing storm sewer and began removing or abandoning fire hydrants and water valves on the old water main system.

South of East Lake Avenue: Next week, the contractor is anticipating to complete the storm sewer improvements. The contractor will also complete the abandonment of the fire hydrants and water valves on the old water main system.

The contractor will begin spot concrete curb & gutter removal and replacements on Longmeadow Drive south of East Lake Avenue the week of August 5th. Additional information will be passed along to residents regarding the procedures during this process, including parking restrictions and access to driveways.  

North of East Lake Avenue: Next week, the contractor will continue the water main testing on the previously installed water main along Bellwood Lane, Ralmark Lane, and Longmeadow Drive. The contractor may begin water services along these roadways should all of the required tests pass.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

The contractor will also directionally drill a new 16-inch water main across Greenwood Road and begin installing a new 16-inch water main approximately 250 south of Bellwood Lane on the east side of Greenwood Road.

Thank you for your patience during the construction operations.

Friday, July 19, 2013

Water Main Installation On-Going North of East Lake Avenue

This past week the contractor installed water valves and vaults, fire hydrants, and made connections between with previously directionally drilled water mains along Bellwood Lane, Ralmark Lane, and Longmeadow Drive north of East Lake Avenue.   

The contractor also completed the directional drilling of the new water main along Ralmark Lane from the cul-de-sac to Bellwood Lane.

No work was completed last week south of East Lake Avenue.

South of East Lake Avenue: Next week, the contractor is anticipating to complete the storm sewer improvements. The contractor will then begin and concrete curb & gutter replacements and paving of the stone trenches. Residents will be notified if any work will affect the access to their driveways.

North of East Lake Avenue: Next week, the contractor will perform water main testing on the previously installed water main along Bellwood Lane and Longmeadow Drive. The contractor will also continue to install fire hydrants, water valve and vaults, and make connections between the previously directional drilled water main along Ralmark Lane. The contractor will also begin directional drilling along Bellwood Lane from Ralmark Lane to Greenwood Road.

Due to the extreme heat conditions, the contractor did work reduced hours throughout the week and did not work on Friday, July 19th.

Thank you for your patience during the construction operations.

Saturday, July 13, 2013

Water Main South of East Lake Avenue Complete

This past week the contractor completed the transferring of water services to the new water main along Longmeadow Drive south of East Lake Avenue. The contractor also completed the connections to the existing water main at Knollwood Lane and Crestwood Lane. The new water main has been completely installed and is 100% operational along Longmeadow Drive from East Lake Avenue to Glenview Road.  

This past week, the contractor also installed water valve vaults, fire hydrants, connections between the previously directionally drilled water main, and connected to the existing water main at Bellwood Lane and Executive Court. The contractor also began directional drilling the new water main along Ralmark Lane on the easterly side from the cul-de-sac to Bellwood Lane.

South of East Lake Avenue: Next week, the contractor is anticipating to complete the storm sewer repairs. The contractor will then begin and concrete curb & gutter replacements and paving of the stone trenches.

North of East Lake Avenue: Next week, the contractor will complete the directional drilling of the water main along Ralmark from the cul-de-sac to Bellwood Lane. The contractor will also begin directional drilling along Bellwood Lane from Ralmark Lane to Greenwood Road. Work will continue along Longmeadow and Bellwood installing the water valve vaults, fire hydrants, and making connections to the previously directionally drilled sections of pipe. Testing of the new water main will likely begin next week prior to starting to install new water services.  

Thank you for your patience during the construction operations.

Monday, July 8, 2013

Water Main Nearly Complete South of East Lake Avenue

This past week the contractor continued to install new water services to individual homes along Longmeadow Drive between Crestwood Lane and East Lake Avenue. The contractor also directionally drilled the new water main along Ralmark Lane from the cul-de-sac to Longmeadow Drive. 

South of East Lake Avenue: The contractor will complete installing the new water services along Longmeadow Drive. The contractor is also anticipating making the connection between the new and existing water mains at the intersections of Knollwood Lane and Crestwood Lane. A water shut down will be required for this work. Residents will be notified 24-hours in advance of any scheduled water main shut down.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

North of East Lake Avenue: The contractor will directionally drill the new water main along Ralmark Lane from the cul-de-sac to Bellwood Drive. The contractor may also begin directional drilling along Bellwood Drive from Ralmark Lane across Greenwood Road.  The contractor will begin installing water valves and fire hydrants along the new water main previously directionally drilled in this area.

Thank you for your patience during the construction operations.