This past week the contractor installed water valves and vaults, fire hydrants, and made connections between with previously directionally drilled water mains along Ralmark Lane and Bellwood Drive north of East Lake Avenue. Testing of the new water main system also began last week.
The contractor also completed directional drilling a new 12-inch water main along Bellwood Lane from Ralmark Lane to Greenwood Road.
Last week, south of East Lake Avenue, the contractor performed various spot repairs to the existing storm sewer and began removing or abandoning fire hydrants and water valves on the old water main system.
South of East Lake Avenue: Next week, the contractor is anticipating to complete the storm sewer improvements. The contractor will also complete the abandonment of the fire hydrants and water valves on the old water main system.
The contractor will begin spot concrete curb & gutter removal and replacements on Longmeadow Drive south of East Lake Avenue the week of August 5th. Additional information will be passed along to residents regarding the procedures during this process, including parking restrictions and access to driveways.
North of East Lake Avenue: Next week, the contractor will continue the water main testing on the previously installed water main along Bellwood Lane, Ralmark Lane, and Longmeadow Drive. The contractor may begin water services along these roadways should all of the required tests pass.
The contractor will also directionally drill a new 16-inch water main across Greenwood Road and begin installing a new 16-inch water main approximately 250 south of Bellwood Lane on the east side of Greenwood Road.