Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
August 2013 – End of Construction

Friday, November 15, 2013

Asphalt Surface South of East Lake Avenue Completed

This past week, Arrow Road, the paving contractor completed paving the asphalt surface along Longmeadow Drive, between Glenview Road and East Lake Avenue.

North of East Lake Avenue along Bellwood Lane, Ralmark Lane, and Longmeadow Drive, the landscaping contractor graded and installed topsoil behind the concrete curb & gutter. Arrow Road performed some asphalt base patching along Bellwood Lane and Greenwood Road. Arrow Road also began driveway restorations along Bellwood Lane including removing the existing pavement and installing the lower layer of asphalt.

The underground sub-contractor was also on-site adjusting manhole frames and lids in preparation of asphalt surface paving.

Next week, Arrow Road is scheduled to pave the asphalt surface along Bellwood Lane, Ralmark Lane, and Longmeadow Drive north of East Lake Avenue. Depending on weather, this work will either begin on Monday or Tuesday and be completed by Tuesday. The contractor will then complete the asphalt driveway restorations along the entire project site on both sides of East Lake Avenue. We anticipate all asphalt driveways will be restored by the end of the week.

Due to the current weather conditions, we are evaluating the options to determine whether or not the sod north of East Lake Avenue will be installed this fall or if it will be better to wait until early next spring.

We continue to appreciate your patience and understanding as we are working diligently to ensure as much work as possible is completed this year. We have been in constant contact with the contractors to determine their schedules and to ensure this project continues to be a priority.