Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
August 2013 – End of Construction

Friday, October 11, 2013

Concrete Curb & Gutter Replacements On-Going north of East Lake Avenue

The project has been transitioned from Glenbrook Excavating, the underground contractor who performed the water main and storm sewer improvements, to Arrow Road. Arrow Road is the general contractor for the Village’s 2013 Road Resurfacing Project (also called MFT). D’Land Construction is a sub-contractor for Arrow Road that will be performing the concrete work.

This past week D’Land construction removed the existing concrete curb & gutter on the north side of Bellwood Lane, west side of Longmeadow Drive, and south and east sides of Ralmark Lane. D’Land also begin installing the concrete curb & gutter in these areas.  The concrete work in these areas of the roadway will continue early next week with the completion of the concrete curb & gutter and concrete driveway installation.

Next week, the contractor will allow the newly installed concrete to cure. The contractor will then move to the opposite sides of the street to begin concrete curb & gutter removal and replacement. Additional notification and parking restrictions will be provided when a firm schedule is determined.

All the roadways within the project limits, including Longmeadow Drive from Glenview Road to East Lake Avenue (area south of East Lake Avenue), Longmeadow Drive from East Lake Avenue to Bellwood Lane (area north of East Lake Avenue), Bellwood Lane from Executive Court to Greenwood Road, and Ralmark Lane from Bellwood Lane to Longmeadow Drive will have the existing asphalt surface milled and repaved as part of this project. This work will not take place until after the concrete curb & gutter replacement north of East Lake Avenue are completed. We are currently working with the contractors to determine the exact start date for the roadway resurfacing, but we are anticipating the work will begin 2 to 3 weeks.

The sod north of East Lake Avenue will not be installed until the concrete curb & gutter and roadway work is completed.

We continue to expression our gratitude for your patience during the construction operations. Your cooperation with the inconvenience associated with the concrete curb & gutter construction is greatly appreciated.