Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
August 2013 – End of Construction

Monday, October 7, 2013

Concrete Curb & Gutter to Begin This Week

This past week the contractor completed installing and grading topsoil in the disturbed areas north of East Lake Avenue. Construction staking in preparation for concrete  curb & gutter was also performed. Village staff started performing the final walk-through to identify any repairs required associated with the underground utility improvements. The final walk-through will hopefully be completed within the next week or so, depending on weather.

The sod north of East Lake Avenue will not be installed until the concrete curb & gutter and roadway work is completed.

Concrete curb & gutter removal along the north side of Bellwood Lane, west side of Longmeadow Drive, and south and east sides of Ralmark Lane is anticipated to begin mid next week, depending on weather conditions.  More information will be provided regarding driveway access and parking while the concrete curb & gutter work is on-going.

We continue to expression our gratitude for your patience and understanding during this long construction season.