Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
August 2013 – End of Construction

Monday, May 6, 2013

The contractor, Glenbrook Excavating, is anticipating to perform work in preparation of installing water main along Longmeadow Drive from Glenview Road to East Lake Avenue. Work includes televising the storm and sanitary sewer, project layout, mobilization of equipment, and excavation for existing utilities.