Last week, south of East Lake
Avenue, the landscaping sub-contractor completed the sod installation. The
contractor also completed some minor work to adjust fire hydrants and valve
boxes.
All underground utility work
has now been completed for the project. The remaining items associated with
this contract to be completed include grading and installing topsoil, site
clean-up, adjustments of structures and fire hydrants, remaining water main
testing, and other miscellaneous tasks. The contractor is currently
scheduled to be on-site through the middle of next week performing most of this
remaining work and complete this portion of the construction.
The landscape sub-contractor is currently scheduled to
install and grade topsoil north of East Lake Avenue next week. The contractor
will install the topsoil within 2 feet of the existing curb & gutter. Sod
will not be installed until after the roadway work has been completed.
All roadways within the project limits will be rehabilitated with the 2013 Road Improvement Program. We are currently working with the contractor to get this work scheduled.
We understand this has been a long summer of construction for all the residents. We appreciate all of your patience and understanding as the underground utility work is complete and we transition to the roadway rehabilitation phase of the project.