Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
August 2013 – End of Construction

Monday, September 30, 2013

Concrete work North of East Lake Avenue to Begin week of October 7th

This past week the contractor completed miscellaneous tasks and clean-up along the entire project site.

The contractor also continued grading and installing topsoil north of East Lake Avenue.

Next week, the landscape sub-contractor will complete the installation and grading of topsoil north of East Lake Avenue. The sod in this area will not be installed until the concrete curb & gutter and roadway work is completed.

The landscape sub-contractor has continued to water the previously installed sod south of East Lake Avenue. The contractor will continue to water until the sod is established and healthy.

We have spoken with the contractor who will be performing the roadway improvements portion of the project. The concrete sub-contractor is expected to begin full concrete curb & gutter removal and replacement north of East Lake the week of October 7th. More information will be provided regarding access to driveways and parking restrictions during concrete curb & gutter work later this week.

We continue to expression our gratitude for your patience and understanding during this long construction season. As stated previously, the underground utility improvements portion of the project is completed, we are now transitioning to the roadway improvements portion.